A Texas district judge has turned down a request to shut the pipeline that carries ethylene to Westlake's polyethylene plant near Longview, the Marshall News Messenger reported on 23 October. Westlake's plant manager had told the court that more than 400 workers would be laid off straight away if the line closed.
The dispute
The case was brought by Larry Wright, owner of Express H2O Pipeline and ROW LLC, who bought an older, disused pipeline several years ago. His lawyers argued that Westlake's line, which runs from Gulf Coast suppliers to the plant, conflicts with the easements attached to his pipeline, and asked for a permanent injunction to close it. A damages claim of more than $100 million was raised early on and later dropped.
After a two-day bench trial in Lufkin, Judge Todd Kassaw of the 159th District Court in Angelina County denied the injunction. He found Wright had not shown that the Westlake pipeline harmed him, and that the easements were not exclusive, so the two lines can coexist. The court did confirm that Wright's easements are older and rank above Westlake's.
"Both sides have some risk on appeal." Brent Coon, attorney for Wright
Another of Wright's lawyers said the company is evaluating the order before deciding what to do next.
Why the line matters
The plant sits inside the Eastman Chemical complex outside Longview and makes polyethylene, which goes into products including bags, bottles and pipe. Most of its ethylene arrives through the disputed line, with some supplied by Eastman. Plant manager Brandon Herber told the court that switching to rail would mean spending millions of dollars on new railcar facilities. Westlake documents shown in court put the plant's yearly economic contribution within 100 miles of Longview at roughly $97 million, and the paper reports the site employs more than 500 people.
What it means for pipe
For HDPE pipe makers, the story is about supply resilience more than price. Polyethylene resin is the main input for pressure and gravity pipe, and a sudden loss of a US PE plant would tighten an already watched supply chain. The ruling removes that risk for now, although a possible appeal means it is not fully closed. It is also a reminder that an inland resin plant can depend heavily on a single feedstock line from the coast.
What it means for hiring
- Resin supply risk is a good reason for pipe makers to invest in procurement and supply chain leaders who understand PE feedstocks, not just finished-goods logistics.
- Plant stability matters to the talent market too. In our view, sites facing legal or supply uncertainty find it harder to hold on to experienced operations and maintenance staff, and competitors often pick them up.
- Anyone recruiting process, quality or plant leadership in East Texas petrochemicals should treat this site as a stable employer for the time being, with an appeal still possible.
Building a team in HDPE Pipe?
Joe Macklam specialises in HDPE Pipe hiring at QP Group. Talk to Joe about the market, salaries or a search.
Sources
- Ruling prevents pipeline shutdown and hundreds of layoffs at Westlake facility in Harrison County · Marshall News Messenger (Longview News-Journal) · 23 Oct 2026
Written by QP Group from the reporting and announcements above. Figures and quotes belong to the original sources.
joe.macklam@qpexec.com
More from The Pipe Line
- Recycled HDPE bale prices rise in October after a flat September26 Oct 2026
- Analyst forecast puts data-centre piping at $4.5B by 2035, with plastics gaining share26 Oct 2026
- IIJA's extra water funding has run out, and contractors want Congress to replace it26 Oct 2026
- Rhode Island lands $38.8M for lead line replacement, well above its usual share26 Oct 2026